Estimation Intialization

Mail Subject : [VL Dev] iRead eBooks

Points of discussion/agreements:

  • Backend features discussion
  • High-level timeline for backend scope 6 months with QC
  • Upon finalizing the BE features list we shall create an excel sheet and add weights per feature (BE/FE) based on the defined project team below with adding phase & sprint columns, and this will be defined in our next meeting.
  • Needed project team will be as follows:
# item Resources
1 Business Analysis 1 senior business analyst

1 Junior business analyst

2 FE Development iOS: 1 Senior, 1 Junior

Android: 1 Senior, 1 Junior

3 BE Development 1 Team Leader .Net

3 Seniors .Net

2 Juniors .Net

4 Quality Control 2 Seniors Quality engineers